TM 9-2350-261-20-2
23. Install new grommet (1) and circuit 10, 14,
15, 27E lead (2) in distribution box (3). In-
stall circuit 10, 14, 15, 27E lead (2) and
circuit 450A lead (4) on bus bar (5). Secure
with new lockwasher (6) and screw (7).
24. For M106A2, M125A2, and M1064, install
new grommet (8) and circuit 6 lead (9) in
distribution box (3). Install circuit 6 lead (9)
on bus bar (5). Secure with new lockwasher
(10) and screw (11).
25. For Ml 13A2, install two new grommets
(8 and 12), circuit 6 lead (9), and circuit 6L
lead (13) in distribution box (3). Install cir-
cuit 6 lead (9) and circuit 6L lead (13) on
bus bar (5). Secure with new lockwasher
(10) and screw (11).
26. Apply one coat of adhesive to cleaned
mounting surface of distribution box (3) and
one side of new gasket (14).
27. Install new gasket (14) on coated mounting
surface of distribution box (3).
FOLLOW-THROUGH STEPS
1. Install master switch panel assembly
3. Start engine (see your 10). Check that
(page 9-16).
distribution box operates properly.
2. Connect battery ground lead (page 13-2).
4. Stop engine (see your 10).
END OF TASK
Change 2
12-51