23. Install two new grommets (1 and 2), cable
assembly W8 lead (3), and circuit 49
lead (4). Install circuit 49 lead (5) and
cable assembly W8 leads (6 and 7) on bus
bar (8). Secure with new lockwasher (9) and
screw (10).
24. Install new grommet (11) and circuit 10,
14, 15, 27E lead (12) in distribution box
(13). Install circuit 10, 14, 15, 27E lead
(14) and circuit 450A lead (15) on bus bar
(8). Secure with new lockwasher (16) and
25. Install new grommet (18) and circuit 6 lead
(19) in distribution box (13). Install circuit 6
lead (24) and cable assembly W8 leads
(20 and 21) on bus bar (8). Secure with
new lockwasher (22) and screw (23).
26. Apply one coat of adhesive to cleaned
mounting surface of distribution box (13)
and one side of new gasket (25).
27. Install new gasket (25) on coated mounting
surface of distribution box (13).
screw (17).
F O L L O W - T O U G H S T E P S
1. Install Master Switch Panel (page 9-16).
3. Start engine (see your -10). Check that
distribution box works properly.
2. Connect battery ground lead (page 13-2).
4. Shutdown engine (see your -10).
END OF TASK