23. Install two new grommets (1 and 2), cable
assembly W8 lead (3), and circuit 49 lead
(4) in distribution box (5). Install circuit 49
lead (4) and cable assembly W8 lead (3) on
bus bar (6). Secure with new lockwasher (7)
and screw (8).
24. Install new grommet (9) and circuit 10, 14,
15, 27E lead (10) in distribution box (5).
Install circuit 10, 14, 15, 27E lead (10) and
circuit 450A lead (11) on bus bar (6). Se-
cure with new lockwasher (12) and
screw (13).
25. Install new grommet (14) and circuit 6 lead
(15) in distribution box (5). Install circuit 6
lead (15) and cable assembly W8 leads (3)
on bus bar (6). Secure with new lockwasher
(16) and screw (17).
26. Apply one coat of adhesive to cleaned
mounting surface of distribution box (5) and
one side of new gasket (18).
27. Install new gasket (18) on coated mounting
surface of distribution box (5).
FOLLOW-THROUGH STEPS
1. Install master switch panel (page 9-16).
3. Start engine (see your -10). Check that
distribution box operates properly.
2. Connect battery ground lead (page 13-2).
4. Shutdown engine (see your -10).
END OF TASK