TM
13.
14.
9-2350-261-20-2
Remove five screws (1), lockwashers (2), and
distribution box (3) from hull. Discard
lockwashers.
Remove gasket (4) from distribution box (3).
Discard gasket.
INSTALL
15. Install distribution box assembly (3) on hull.
Secure with five new lockwashers (2) and
screws (1).
16. Install new grommet (5) and circuit 2 lead
(6) in distribution box (3).
17. Install new grommet (7) and circuit 400
lead (8) in distribution box (3).
NOTE
If bilge pump circuit breakers were
removed,
r e f e r t o p a ge
16-12 for
installation.
I f b i l g e p u m p c i r c u it
breakers were not removed, go to step 21.
19.
20.
21.
22,
23.
24.
Install circuit 450C lead (9) on bus bar (11).
Secure with new lockwasher (12) and
screw (13).
Connect circuit 450A lead (14) to circuit
breaker (15).
Install new grommet ( 16) and circuit 450B
lead (17) in distribution box (3). Connect cir-
cuit 450B lead to circuit breaker (18).
Install new grommet ( 19) and circuit 450
lead (20) in distribution box (3). Connect cir-
cuit 450 lead to circuit breaker (21).
Install new grommet (22) and circuit 3 lead
(23) in distribution box (3). Install circuit 3
lead on circuit breaker (24). Secure with
new lockwasher (25) and screw (26).
Install wiring harness (27) on bus bar (11).
Secure with new lockwasher (28) and
screw (29).
18. Connect circuit 450C lead (9) to circuit
breaker ( 10).
12-30