TM 9-2350-261-20-2
21. Install new grommet (1) and circuit 49 lead
(2) in distribution box (3). Install circuit 49
lead (2) on bus bar (4). Secure with new
lockwasher (5) and screw (6).
22. Install new grommet (7) and circuit 10, 14,
15, 27E lead (8) in distribution box (3). In-
stall circuit 10, 14, 15, 27E lead (8) and
circuit 450A lead (9) on bus bar (4). Secure
with new lockwasher (10) and screw (11).
23. Install new grommet (12) and circuit 6 lead
(13 ) in distribution box (3). Install circuit 6
lead (13 ) on bus bar (4). Secure with new
lockwasher (14) and screw (15).
24. Apply one coat of adhesive to cleaned
mounting surface of distribution box (16)
and one side of new gasket (17).
25. Install new gasket (17) on coated mounting
surface of distribution box (16).
FOLLOW-THROUGH STEPS
1. Install master switch panel (page 9-16).
3. Start engine (see your -10). Check that
distribution box operates properly.
2. Connect battery ground lead (page 13-2).
4. Stop engine (see your 10).
END OF TASK
12-43
