INITIAL SETUP
Tools:
General Mechanics Tool Kit (Item 35, App B)
Materials/Parts:
Dry cleaning solvent (Item 18, App C)
Sealing compound (Item 70, App C)
Sealing compound primer (Item 74, App C)
Kit P/N 12268857 (19207)
Personnel Required:
Track Vehicle Repairer 63H10
References:
See your -10
See your -20
Equipment Conditions:
Ramp lowered (see your -10)
Engine stopped/shutdown (see your -10)
Carrier blocked (see your -10)
Fuze rack removed (M106A2)
(see your -20)
Fire extinguisher removed
(M106A2 and M125A2) (see your -20)
Battery ground lead disconnected
(see you -20)
Power plant rear access panel removed
(see your -20)
Floor plates removed (see your 20)
Front horizontal ammunition racks and
supports removed (M106A2 and M125A2)
(see your -20)
Fuel compartment drained
(M106A2 and M125A2) (see your -20)
1.
2.
3.
Remove six screws (1), two plates (2), and
gaskets (3) from top of carrier. Discard
screws, plates, and gaskets.
Remove nut (4) and screw (5) from
transverse beam. Discard nut and screw.
Remove nut (6) and screw (7) from power
plant compartment bulkhead. Discard nut and
screw.
GO TO NEXT PAGE
Change 2
11-15
INSTALL