TM 9-2350-261-34
7.
8.
9.
10.
11.
12.
13.
Remove and discard cradle clip (1), move
14.
battery lead (2) aside.
Remove screw (3) and cradle (4) from
15.
weldnut (5). Discard screw and cradle.
16,
Install grommet (6) in power plant
bulkhead.
Install exhaust pipe (7) in grommet (6).
Install exhaust pipe (8) on exhaust pipe (7).
Secure two exhaust pipes (8 and 9) and two
gaskets (10) to power plant bulkhead with
four screws (11) and retained nuts (12).
Install gasket (13) on exhaust elbow (14)
and insert elbow through top deck into
exhaust pipe (9).
Install gasket (15) on intake elbow (16) and
position elbow through top deck opening.
Secure exhaust and intake elbows
(14 and 16) to top deck with six
screws (17).
Secure exhaust pipe (9) to elbow (14) with
U-bolt (18), clamp (19), and two nuts (20).
GO TO NEXT PAGE
11-3