Align hole in governor throttle arm (1) with
hole in gage (2). Insert screw (3) through
throttle arm and gage.
Insert 3/16 inch (5 mm) key socket head
screw in plug on top of governor shaft (4).
Turn to the right to rotate governor shaft
(4) to full throttle positional hold.
Tighten screw (5) that secures throttle arm
(1) to governor shaft (4).
Remove screw (3) installed in step 5, above.
Remove two screws (6) that secure gage (2)
to governor (7) and return gage to stowed
position. Secure gage with two screws (6).
Connect throttle link (7) to governor throttle
arm (1). Secure with screw (3) and nut (8).
N O T E
On M741A1 carrier, the clearance be-
tween screw (3) and lockout solenoid
must
be
checked
at
this
point
(page 28-74).
11. Adjust throttle valve linkage.
ADJUST THROTTLE VALVE
LINKAGE
12. Turn screw (9) into floor bracket (10) to
allow free movement of accelerator
pedal (11).