TM 9-2350-261-20-2
INSTALL
N O TE
If plug (11) was removed, clean and apply
a thin coat of sealing compound (Item 46)
on threads before installing.
5.
6.
7.
8.
Connect coolant tube (1) to hose (2) with two
clamps (3). Tighten two clamps (3).
Connect coolant tube (1) and elbow (4) with
hose (5) and two clamps (6). Tighten two
clamps (6).
Apply a thin coat of sealing compound
(Item 48) to both sides of new gasket (7).
Install new gasket (7) between elbow (4) and
engine. Secure with two flat washers (8), new
lockwashers (9), and screws (10). Tighten
screws to 360-384 lb-in (41-43 Nm) torque.
Use torque wrench.
FOLLOW-THROUGH STEPS
1. Fill cooling system (page 85).
3. Stop/shutdown engine (see your 10).
2. Start engine (see your 10). Check for leaks.
4. Close power plant front access door and raise
trim vane (see your -10).
END OF TASK