This task covers:
Remove (Page 6-140).
Install (Page 6-141).
INITIAL SETUP
Tools:
References:
General Mechanics Tool Kit (Item 30, App D)
See your -10
Materials/Parts:
Equipment Conditions:
Sealing tape (Item 56, App C)
Engine stopped/shutdown (see your -10)
Battery ground lead disconnected (page 13-2)
Personnel Required:
Carrier blocked (see your -10)
Unit Mechanic
Trim vane lowered and power plant front
access door open (see your -10)
1.
2.
3.
Disconnect air box heater wiring harness con-
nector (1) from power plant wiring harness
receptacle (2).
Disconnect wiring harness connector (3) from
coil (4).
Remove two nuts (5), washers (6), and two
wiring harness leads (7) from air pump (8).
4.
5.
6.
Disconnect wiring harness connector (9) from
fuel control solenoid (10).
Remove screw (11), washer (12), and three
ground leads (13) from air box heater (14).
Remove strap (15), sealing tape (16), air box
heater wiring harness (17) from power plant
compartment.
6-140