50.
51.
Connect ramp hydraulic line at coupling (1)
(all except M741A1).
Connect ramp hydraulic line at coupling (2)
(all except M741A1).
52. Install clamp (3), on radiator inlet tube (4).
Secure clamp to hanger (5) with washer (6),
screw (7), and nut (8).
NOTE
Screws and washers must be clean, dry,
and free of lubricants and paint. If your
carrier is equipped with 6C universal
joints, screws are 3/8-24 x 1-3/4; if
equipped with 7C universal joints, screws
are 1/20 x 2.
53. Connect propeller shaft (9) to transmission
with four new flat washers (10) and four
new screws (11). Use torque wrench
(Item 96) and adapter to tighten screws. On
6C universal joints, tighten to 35-40 lb-ft
(47-54 Nm) torque, and on 7C joints,
tighten to 83-100 lb-ft (113-136 Nm)
torque, then loosen screws and tighten them
to the correct torque again. See page 2-29
for correct readings on torque wrenches with
adapters.
54. Install L&R final drive propeller shafts
(page 20-5 and 20-7).
I
TM 9-2350-261-20-1
5-20