TM 9-2350-247-20-2
0206 00
INSTALLATION
1.
Place muffler (3) on power plant compartment bulkhead. Secure with four screws (4), eight washers (5), and four new
lock nuts (6). Tighten screws to 240-300 lb-in (27-34 Nm) torque.
2.
Install interior exhaust pipe (2) on muffler (3). Secure with clamp (1). Tighten clamp to 200-220 lb-in (23-25 Nm)
FOLLOW-THROUGH STEPS
1.
Turn MASTER SWITCH ON (see your -10).
2.
Start engine (see your -10).
3.
Check for proper installation of muffler.
4.
Stop engine (see your -10).
5.
Install top access cover (WP 0390 00).
6.
Install power plant rear access door (see your -10).
END OF TASK