TM 9-2350-261-20-2
INSTALL
7.
8.
9.
Place new preformed packing (1) on new fi-
nal drive adapter (2).
Grease speedometer shaft (3)
(see your -LO).
Place adapter (2) on final drive, and secure
-
with four new key washers (4) and screws
(5). Bend keys on washers.
NOTE
Remove clamps and install on new cable.
10.
11.
12.
13.
Install new grommet (6) on new cable (7),
and route cable through drivers compart-
ment bulkhead.
Install grommet (6) in bulkhead.
Install slotted washer (8), flat washer (9),
on speedometer cable (7) to flnal drive
adapter (2).
Install speedometer cable (7) with new
ket (10) on speedometer (11).
14. Align two clamps ( 12) with bulkhead weld-
nuts and secure with two new lockwashers
(13) and screws (14).
gas-
FOLLOW-THROUGH STEPS
1. Install hull front access cover (page 24-24).
3. Raise trim vane (see your -10).
2. Close power plant front door (see your -10).
END OF TASK
11-18