REPLACE AIR BOX HEATER HOSES, TUBES, AND FITTINGS (M548A3) -- Continued
0181 00
INSTALLATION
1.
Install new fittings if needed.
2.
Install hose (1) on check valve (2) and air pump (3).
3.
Connect heater hose (4) on check valve (2) and elbow (5).
4.
Place clamp (6) on heater hose (4). Install hose and clamp to engine with screw (7) and washer (8).
5.
Wrap electric leads and heater hose (4) with spiral tubing (9) in two places.
6.
Connect fuel hose (10) to elbow (11).
7.
Connect fuel hose (10) to fuel line tee (12).
8.
Install two clamps (13) on hose (10) with two screws (14) and washers (15).
FOLLOW-THROUGH STEPS
1.
Install power plant rear access panel (see your -10).
2.
3.
4.
Lower center seat (see your -10).
END OF TASK