TM 9-2350-277-20-5
REPLACE IGNITER
0730 00
THIS WORK PACKAGE COVERS:
Removal (page 0730 00-1).
Inspection (page 0730 00-2).
Installation (page 0730 00-2).
INITIAL SETUP:
Maintenance Level
Unit
Tools and Special Tools
General Mechanics Tool Kit (WP 0926 00, Item 65)
Materials/Parts
Gasket
Lockwasher
Personnel Required
Unit Mechanic
References
See your -10
Equipment Condition
Engine stopped (see your -10)
Carrier blocked (see your -10)
Trim vane lowered (see your -10)
Power plant access door open (see your -10)
Battery ground strap disconnected (WP 0337 00),
(WP 0338 00), or (WP 0339 00)
Air cleaner removed (WP 0168 00)
REMOVAL
1.
Loosen four nuts (1). Turn cover plate (2) to the left and remove.
2.
Remove screw (3), lockwasher (4), igniter ground lead (5), and ground strap (6) from coolant heater. Discard lockwasher.
3.
Remove two nuts (7) and resistor strap (8) from igniter (9). Bend strap out of way.
4.
Remove igniter (9) and gasket (10) from heater. Discard gasket.
0730 00-1