TM 9-2350-261-20-1
R A I S E / L O W E R P O W E R P L A N T G R I LL
D E S C R I P T I O N
This task covers: Raise (page 5-2).
Lower (page 5-6).
INITIAL SETUP
Tools:
General Mechanics Tool Kit (Item 30, App D)
Antifreeze and Battery Tester,
(Item 74, App D)
Socket Wrench Set (Item 90, App D)
Torque Wrench (Item 97, App D)
Torque Wrench (Item 98, App D)
Materials/Parts:
Antifreeze (Item 8, App C)
Caulking compound (Item 8, App C
Self-locking nut (2)
Tab washers (4)
Personnel Required:
Unit Mechanic
Helper (H)
References:
see your -lo
TM 92350-300-10
Equipment Conditions
Engine stoppedlshutdown (see your -10)
Carrier blocked (see your -10)
Trim vane lowered (see your -10)
Power plant front access door open
(see your -10)
Drivers power plant access panel removed
(page 24-25)
Power plant rear access panel removed
(page 24-27 or 24-29)
Generator set removed (M577A2 only)
(see your -10)
Battery ground lead disconnected (page 13-2)
R A I S E G R I L L
1.
2.
Release four latches (1). Remove air cleaner
housing (2) and element (3) from cover (4).
Disconnect electrical cable (5) at drivers
compartment bulkhead. Remove screw (6),
clamp (7), and cables from weldnut (8).
5-2