TM 9-2350-247-20-2
REPLACE THROTTLE PEDAL LINKAGE (M548A1) -- Continued
0197 00
INSTALLATION
1.
Install bearing (1) in throttle control link (2). Secure with jam nut (3).
2.
Install control bracket (4) on power plant. Secure with three screws (5) and two new lock nuts (6).
3.
Install engine fuel return elbow in control bracket (4) (WP 0167 00).
4.
Install two bearings (7) in transfer shaft (8).
5.
Install transfer shaft (8) in control bracket (4).
6.
Install pivot rod (9) through transfer shaft (8). Secure with new cotter pin (10).
7.
Install pin (11) in transfer shaft (8). Secure with new cotter pin (12).
8.
Install governor control link (13) through pin (11). Secure link to governor arm with screw (14) and new lock nut (15).
9.
Install spring (16) and washer (17) on governor control link (13). Secure with new cotter pin (18).
10. Install throttle control link (2) on transfer shaft (8). Secure with screw (19) and new lock nut (20).