TM 9-2350-247-20-1
REMOVE/INSTALL POWER PLANT (M548A1) Continued
0130 00
NOTE
Install mounting clamps so nuts are on inboard and forward sides of mounts.
2.
Install transfer gearcase mounting clamps.
a.
Install mounting clamp (2) to secure right transfer gearcase mount (3) to hull.
b.
Install mounting clamp (4) to secure left transfer gearcase mount (5) to hull.
3.
Install two screws (6) with two new washers (7) in front engine mount (8). Tighten screws finger tight.
4.
(H) Lower beam type sling (1) and detach from power plant.
5.
Tighten two screws (6) securing front engine mount (8) to hull to 120-130 lb-ft (163-176 Nm) torque.
0130 00-15