INSTALLATION
1.
Apply light coat of sealing compound to external tapered threads of elbow (5). Do not apply sealing compound beyond
small end of tapered threads.
2.
Install elbow (5) in engine block fitting (7). Install adapter (6) in elbow (5).
3.
Install clamps (1) and (4) on hose (3).
4.
Connect hose (3) to elbow (5) and shutoff valve (2). Tighten clamps (1) and (4).
FOLLOW-THROUGH STEPS
1.
Install air cleaner (WP 0168 00).
2.
Fill coolant heater system (WP 0710 00).
3.
Start coolant heater (see your -10). Check for leaks. Turn heater off.
4.
Close power plant access door (see your -10).
5.
Raise trim vane (see your -10).
6.
Install power plant rear access panel (see your -10).
7.
Start engine (see your -10).
8.
Raise and lock ramp (see your -10).
9.
Stop engine (see your -10).
END OF TASK