TM 9-2350-277-20-3
REPLACE MASTER SWITCH PANEL DOME LIGHTS LEAD ASSEMBLY (M577A3 AND
M1068A3 ONLY) Continued
0380 00
INSTALLATION
1.
Replace gasket (11) if damaged.
2.
Place new grommet (10) on branch of lead assembly (6) that connects to circuit 38E lead (9).
3.
Install lead assembly (6) with grommet (10) in master switch panel (4).
4.
Connect lead assembly (6) to circuit 38E lead (9), circuit breaker (8), and front dome light switch (7).
5.
Place master switch panel (4) on distribution box (5). Secure with eight screws (3), washers (2), and new locknuts (1).
FOLLOW-THROUGH STEPS
1.
Connect battery ground lead (WP 0338 00).
2.
Turn MASTER SWITCH ON (see your -10).
3.
Operate dome lights to check that lights operate properly (see your -10).
4.
Turn all switches OFF (see your -10).
END OF TASK