REPLACE MASTER SWITCH PANEL DOME LIGHTS LEAD ASSEMBLY
(M577A3 AND M1068A3 ONLY)
0380 00
THIS WORK PACKAGE COVERS:
Removal (page 0380 00-1).
Installation (page 0380 00-3).
INITIAL SETUP:
Maintenance Level
Unit
Tools and Special Tools
General Mechanics Tool Kit (WP 0926 00, Item 65)
Materials/Parts
Gasket
Grommet
Locknut (8)
Personnel Required
Unit Mechanic
References
See your -10
Equipment Condition
Engine stopped (see your -10)
Carrier blocked (see your -10)
Battery ground lead disconnected (WP 0338 00)
REMOVAL
1.
Remove eight locknuts (1), washers (2), screws (3), and master switch panel (4) from distribution box (5). Discard
locknuts.
2.
Disconnect lead assembly (6) from front dome light switch (7), circuit breaker (8), and circuit 38E lead (9).
3.
Pull lead assembly (6) with grommet (10) from master switch panel (4). Discard grommet.