TM 9-2350-261-20-4
REPLACE COOLANT HOSES AND FITTINGS
THIS WORK PACKAGE COVERS:
INITIAL SETUP:
Maintenance Level
Equipment Condition
Unit
Engine stopped (see your -10)
Carrier blocked (see your -10)
Tools and Special Tools
Trim vane lowered (see your -10)
Power plant front access door open (see your -10)
Materials/Parts
Power plant rear access panel removed (WP 0431 00,
WP 0432 00, or WP 0433 00)
Carrier cooling system drained (WP 0193 00)
Gasket
Grommet (2)
Personnel Required
Unit Mechanic
REMOVAL
1.
Loosen six clamps (1) on hoses (2), (3), and (4). Remove hose (2) from adapter (5) and tee (6). Remove hose (3) from
tee (6) and radiator auxiliary tank (7). Remove hose (4) from tee (6) and thermostat housing on engine.
2.
Remove six clamps (1) from hoses (2), (3), and (4).
3.
Remove two screws (8) and clamps (9) from two hull weldnuts.