TM 9-2350-247-20-3INSPECT POWER PLANT SLING — Continued 0443 00NOTEUse straight edge to measure cross beam bend.7. Inspect structural members for following:a. If welded joints are cracked in excess of 1/2 inch (13 mm) or 25% of length of weld in gusset (1) to cross beam (2)area, remove sling from service.b. If cross beam is bent or twisted in excess of 1/4 inch (6 mm) at ends of cross beam, remove sling from service. Donot attempt to straighten a bent cross beam.c. If lifting hole (3) is elongated in excess of 1/8 inch (3 mm), remove sling from service.8. Complete required forms.PREOPERATIVE CHECKWARNINGDamaged lifting slings can fall with load. Personnel can be injured or killed. Inspect all slings.Do not use damaged slings.NOTEChains are inspected on a link by link basis with the chain slack.1. Do Periodic Check Procedure Step 2a and Steps 3 - 8.END OF TASK0443 00-7/8 blank