TM 9-2360-261-20-2
INSTALL
6.
7.
8.
9.
10.
11.
Remove backing from new gasket (1). Install
gasket, sticky side down. and sight glass (2)
on upper pipe (3). Secure with two Ubolts
(4), four washers (5), and new locknuts (6).
Tighten nuts to 12 lb-in (1 Nm) torque.
Use torque wrench and socket wrench set.
Install new grommet (7) in drivers compart-
ment bulkhead.
Install clamp (8), hose (9), and two clamps
(10) on upper pipe (3).
Slide pipe (3) through grommet (7) and in-
stall upper end on discharge outlet. Secure
with two clamps (10).
Install clamp (8), two hoses (11), and four
clamps (12) on lower pipe (13).
Slide pipe (13) on upper pipe (3) and bilge
pump. Secure with four clamps (12).
12. Align two clamps (8) with two bulkhead
weldnuts, Secure with two washers (14) and
screws (15) .
FOLLOW-THROUGH STEPS
1. Install front bilge pump strainer (page 16-3,
3. Install hull front access cover (page 24-24).
steps 15 thru 18).
4. Close power plant front access door
2. Turn MASTER SWITCH ON (see your -10).
(see your -10).
Operate bilge pump and check for leaks. Turn
all switches OFF (see your -10).
5. Raise trim vane (see your -10).
END OF TASK