11-3. TORSION BAR ANCHOR REPLACEMENT (continued).
4.
Apply sealer around entire edge of cover plate (1,3, or 4).
5.
Install cover plate (1 or 4) on hull floor with 10 screws (2).
6.
Install cover plate (3) on crew compartment floor with 16 screws (2).
NOTE
Make sure conveyor hydraulic hoses are routed between two plates when installing.
7.
Position two hydraulic hoses (8) between two plates (5) on cover plate (3). Secure two plates (5) and electrical
lead (9) with four screws (6) and new Iockwashers (7).
FOLLOW-ON MAINTENANCE:
Install powerpack (torsion bar anchor positions 1 and 2) (para 3-2).
Install heating and ventilation duct (torsion bar anchor positions 4 and 5) (para 16-2).
Install projectile rack assembly base (torsion bar positions 4 and 5) (para 15-82).
Install torsion bar (para 11-2).