TM 9-2350-287-20-2
15-83. PROJECTILE RACK REPLACEMENT (continued).
NOTE
Step 4 applies only to left projectile
rack.
4.
Install bracket (7) and spacer (6) to
outside APU compartment wall (5) with
two screws (10), new Iockwashers (9),
and washers (8).
5.
Adjust bracket (7) to provide snug fit on
rack assembly (3).
6.
Remove hook (2) from bar (1).
FOLLOW-ON MAINTENANCE:
Close top doors (refer to TM 9-2350-287-10).
l Install right projectile rack stowage box guard
plate assembly (para 15-81).