TM 9-2350-287-20-1
7-22. APU CONTROL BOX REPAIR (continued).
6.
Install gage bracket (45) on gage (12) with two new Iockwashers (44) and nuts (43).
7.
Install each of three circuit breakers (15, 31 and 32) on control box (8) with two nuts (41), new Iockwashers
(40), and screws (42)
8.
Connect ground wire (38) to preheat switch (35).
9.
Connect
10.
Connect
wire 487A (34) to preheat switch (35) and circuit breaker (31).
wire 65A (37) to start switch (28).
7-71