TM 9-2350-277-34
SERVICE UPON RECEIPT
0013 00
THIS WORK PACKAGE COVERS:
Service upon receipt (Checking Unpacked Equipment).
INITIAL SETUP:
Maintenance Level
Direct Support
Tools and Special Tools
General Mechanics Tool Kit (WP 0120 00, Item 62)
Personnel Required
Track Vehicle Repairer 63H10
References
TM 9-2350-277-10
TM 9-2350-277-20
Equipment Condition
Engine stopped (see your -10)
SERVICE UPON RECEIPT OF MATERIEL
Checking Unpacked Equipment
This section provides information on how to check and service your carrier when it is received. Level B and A deprocessing
procedures are given in the following table. Level B deprocessing is performed when the carrier have been in storage for less
than ninety (90) days. Level A deprocessing is performed, in addition to Level B deprocessing, when the carrier has been in
storage for more than 90 days.
SERVICE UPON RECEIPT
LOCATION
ITEM
ACTION
REMARKS
Hull
Drivers Hatch
Remove welded nut/bolt from drivers hatch to gain vehicle
entry
Engine
Engine Air Intake
(1) Remove air restrictor plug from air duct at air
filter.
(2) Connect filter host to air filter.
(3) Remove warning tag.
Engine
Fuel lines
(1) Connect fuel lines at quick disconnect.
(2) Connect fuel supply tubing.
Engine
Crankcase
Remove shipping tape from crankcase breather.
Engine
Oil level gauge
Remove shipping tape from oil level gauge rod opening.
Engine
Caps and plugs
Remove caps and plugs from all openings to engine that
vent outside.
Engine
Power plant access
panels
Install power plant access panels.
Hull
Carrier batteries
(1) Remove shipping tape from filler caps.
(2) Add electrolyte and charge batteries. See
TM 9-6140-200-14.
Hull
Battery Cables
Install cables on battery . See your -20.
0013 00-1