TM 9-2350-261-34
2. Measure any voids in foam. Repair any single
NOTE
void larger than 8.0 square inches (52 sq cm)
Indentations in shell or foam caused by
in area by 0.75 inch (19 mm) deep. If total
contact with carrier hardware during
volume of voids in both trim vane pods
operation or during manufacturing pro-
(1 and 2) exceeds 100 cubic inches (1639 cu
cedures need not be repaired.
cm), repair the foam. If total volume of voids
in either set of three hull side pods (3 and 4)
3. Inspect any previous repairs for conformance
exceeds 140 cubic inches (2295 cu cm), repair
with repair criteria below.
the foam.
NOTE
Hull side flotation pods (items 3 and 4)
M741A1 only.
GO TO NEXT PAGE
Change 1
8-23