10. Install three clamps (1), screws (2), and new lock nuts (3) securing power plant wiring harness (4) to brackets.
11. Connect circuit 327 lead (5) to transmission oil high temperature switch (6).
12. Connect circuit 328 lead (7) to differential oil high temperature switch.
13. Install two clamps (8), screws (9), new lock washer (10), and new lock nuts (11) securing power plant wiring harness (4)
on top of bracket (12) and cross-shaft (13).
14. Connect circuit 6 connector (14) and multiple connector (15) to battery compartment bulkhead.
FOLLOW-THROUGH STEPS
1.
Install hull bottom access cover (see your -10).
2.
Connect battery negative lead (see your -20).
3.
Lower cab personnel center seat and drivers seat (see your -10).
END OF TASK