TM 9-2350-277-34
INSTALL PERSONNEL HEATER KIT (M113A3, M1059A3, AND M58 ONLY) Continued
0072 00
77. Install clamp (1) on battery cable (2), radio cable (3), and personnel heater wiring harness (4).
78. Secure clamp (1) and personnel heater wiring harness ground lead (5) to weldnut (6) with retained screw (7), lockwasher
(8), and flat washer (9).
FOLLOW-THROUGH STEPS
1.
Open both main fuel tank shutoff valves and heater fuel shutoff valve. (see your -10).
2.
Bleed air from heater fuel lines (see your -20).
3.
Connect battery ground strap (see your -20).
4.
Start personnel heater (see your -10). Check heater installation for proper operation and leaks. Turn heater off.
5.
Install power plant rear access panels (see your -20).
6.
Install rear floor plates (see your -20).
7.
Start engine (see your -10).
8.
Raise and lock ramp (see your -10).
9.
Stop engine (see your -10).
END OF TASK
0072 00-17/18 blank