TM 9-2350-277-34
INSTALL PERSONNEL HEATER KIT (M113A3, M1059A3, AND M58 ONLY) Continued
0072 00
7.
Install grommet (10) in power plant bulkhead.
8.
Install exhaust pipe (11) in grommet (10).
9.
Install exhaust pipe (12) on exhaust pipe (11).
10. Secure two exhaust pipes (12) and (13) and two gaskets (14) to power plant bulkhead with four screws (15) and retained
locknuts (16).
11. Install gasket (17) on exhaust elbow (18) and insert elbow through top deck into exhaust pipe (13).
12. Install gasket (19) on intake elbow (20) and position elbow through top deck opening.
13. Secure exhaust and intake elbows (18) and (20) to top deck with six screws (21).
14. Secure exhaust pipe (13) to elbow (18) with loop clamp (22).
0072 00-4