TM 9-2350-261-20-4
REPLACE POWER CONTROL ENCLOSURE AC AND DC METERS AND LIGHT
0729 00
INDICATORS (M1068 ONLY) -- Continued
INSTALLATION
1.
If bulb (1) or lens (2) was removed, install on indicator light (3).
Install two indicator lights (3) on faceplate (4). Secure with two new lockwashers (5) and jamnuts (6).
2.
3.
Install meter M2 (7) on faceplate (4). Secure with three screws (8) and new locknuts (9).
4.
Install meter M1 (10) on faceplate (4). Secure with three screws (8) and new locknuts (9).
Install circuits 32F (11) and 28C leads (12), washer (13), and nut (14) on negative (-) terminal of meter M2 (7).
5.
6.
Install circuit 31F lead (15), washer (13), and nut (14) on positive (+) terminal of meter M2 (7).
7.
Install circuit 30A lead (16), washer (17), and nut (18) on terminal 1 of meter M1 (10).
8.
Install circuit 29A lead (19), washer (17), and nut (18) on terminal 2 of meter M1 (10).