TM 9-2350-261-20-1
E N G I N E R U N S R O U G H , S T A L L S , O R D O E S N O T P U T O U T F U L L
P O W E R
INITIAL SETUP
Tools:
General Mechanics Tool Kit (Item 30, App D)
STE/ICE-R Test Set (Item 71.1, App D)
Materials/Parts:
Suitable container
Wiping rag
Personnel Required:
Unit Mechanic
Helper (H)
References:
See your -10
References (cont):
See your LO
STE/ICE-R Test 14 (page 3-287)
Equipment Conditions:
Engine stopped/shutdown (see your -10)
Carrier blocked (see your -10)
Air cleaner element cleaned (see your -10)
Primary and secondary fuel filters serviced
(see your -10)
Trim vane lowered (see your -10)
Power plant access door
Power plant rear access
(see your -10)
Rear compartment floor
(page 24-37)
open (see your -10)
panels removed
plates removed
1. Ensure manual shutoff valve is open (see your -10).
2. Push forward on quick disconnect coupling (1) to discon-
nect return hose (2) from fuel return line (3).
CAUTION
Keep return hose clear of generator
drive belts.
3. Pull return hose (2) with quick disconnect coupling (1)
out of power plant compartment. Remove half of quick
disconnect coupling (1) from return hose (2), and retain.
3-44
Change 1